Beebe Medical Center – Rollins Addition

Contract Amount: $4,850,000.00
Lewes, Delaware
Owner: Beebe Hospital
Customer: Wohlsen Construction

The new 57,000 square foot space expands the emergency department of this hospital from 18 to 36 beds, the critical care unit is increased from 12 to 20 beds and an additional 42 medical surgical beds are now available.

Delcard Associates played the vital role in providing the complete plumbing and HVAC systems that supported this addition. The new addition houses a new medical air and vacuum system for the entire hospital as well. The Delcard team fabricated and installed 92,000 lbs of sheet metal duct. The new steam pressure reducing station, used to manage the steam to make that hot water conversion was fabricated in Delcard’s pipe fabrication facility.